A service is not ready for production when its code works; it is ready when the people who will run it at 3 a.m. can tell it is broken, know what to do, and can undo a bad change in minutes. A production readiness review (PRR) checks that before launch, against a written list: SLOs and alerts, capacity, failure testing, security, rollback, backups, and runbooks. Handover is the same idea when a service moves from the team that built it to a team that will operate it. This lesson follows one service from feature-complete to a sustainable on-call rotation, and shows what skipping the review costs and how a late blocker stretches the plan.
Difficulty: Advanced · Know this first: Lesson 158, Lesson 162, Lesson 157
This bar splits the time from feature complete to a sustainable on-call rotation, in working days. It is a worked example, not a measurement. Much of the readiness work can run in parallel; the bar shows it end to end.
Set how many pages the service sends a week and how many people share the rotation. The guidance from Google's SRE book is at most about two incidents per 12-hour shift.
pages per 12-hour shift = pages per week ÷ 14 · on-call days per person per week = 7 ÷ people · sustainable at about 2 or fewer per shift
Sustainable: hand it over
Three questions. No score is saved anywhere — this is just you against the material.
Readiness grows in four levels: first why working code is not enough, then running a checklist, then running reviews and handovers well, and finally making readiness part of how an organization ships.
At the basic level you can list what a service needs before production besides working code: a definition of good (SLOs), a way to see it (dashboards), a way to be told it is broken (alerts), instructions for fixing it (runbooks), proof it can carry the load, proof it survives failures, a security review, a way to undo changes, and backups that restore.
Terms: PRR, launch checklist, blocker, follow-up, game day, runbook, handover, shadow week.
Where it breaks: launch dates set before the readiness work is estimated.
Try it: Basic
Which of these is a typical launch blocker?
Now do it: Run readiness.py in Go deeper and mark one more item undone. Decide whether it should be a blocker.
At the intermediate level you run the checklist for a service.
Troubleshooting: items that are "done" without evidence are not done; ask for the link.
Try it: Intermediate
A team marks "load tested" as done but has no report. What do you do?
Now do it: Pick a service you run and gather the evidence links for every item in the checklist in Go deeper.
At the advanced level you run reviews and handovers across teams.
Try it: Advanced
A service passes its PRR, but six months later pages twice as often and its runbooks are stale. What is missing?
Now do it: Write the handover criteria your on-call team would accept, and the conditions under which they may hand a service back.
At the master level readiness is built into how the organization ships.
Trade-off: a heavy review for every change slows everyone and gets skipped; no review ships fast and pays at night. Tier the reviews by risk and automate the evidence.
Try it: Master
Teams complain the PRR takes weeks. What reduces it without losing safety?
Now do it: Mark which items in your checklist a golden path could satisfy by default.
A readiness review is data: items, evidence, and which missing items block the launch. This script evaluates a checklist and checks whether a rotation can carry the service's page load. Standard library only; python3 readiness.py.
# readiness.py - a production readiness review as data: blockers stop a launch, the rest is a plan
CHECKS = [ # (area, item, done, blocker if missing)
("SLOs", "availability and latency SLOs agreed with the product owner", True, True),
("Observability", "dashboard with the four golden signals", True, True),
("Observability", "burn-rate alerts that page, with runbook links", True, True),
("Capacity", "load test at 2x expected peak, results recorded", True, True),
("Resilience", "dependency failure tested: database failover, slow downstream", False, True),
("Security", "threat model reviewed; no secrets or PII in logs", True, True),
("Release", "canary and one-command rollback, practised", True, True),
("Operations", "runbooks for the top five alerts", True, False),
("Operations", "on-call shadow week completed by the receiving team", False, False),
("Data", "backups restored once, time recorded", True, True),
]
blockers = [f"{a}: {i}" for a, i, done, b in CHECKS if not done and b]
follow_ups = [f"{a}: {i}" for a, i, done, b in CHECKS if not done and not b]
print(f"{sum(d for _, _, d, _ in CHECKS)} of {len(CHECKS)} checks done")
print("launch:", "BLOCKED" if blockers else "approved")
for b in blockers:
print(" blocker: ", b)
for f in follow_ups:
print(" follow-up:", f)
# Can the receiving team carry the pager? Google's SRE book suggests at most about 2 incidents per 12-hour shift.
for name, pages_per_week, people in [("ledger", 6, 6), ("ledger, noisy alerts", 40, 6)]:
per_shift = pages_per_week / 14 # two 12-hour shifts a day, seven days
print(f"{name}: {pages_per_week} pages a week -> {per_shift:.1f} per 12-hour shift"
f" ({'sustainable' if per_shift <= 2 else 'too many: fix the alerts before handover'}),"
f" each of {people} people on call {7 / people:.1f} days a week")
$ python3 readiness.py 8 of 10 checks done launch: BLOCKED blocker: Resilience: dependency failure tested: database failover, slow downstream follow-up: Operations: on-call shadow week completed by the receiving team ledger: 6 pages a week -> 0.4 per 12-hour shift (sustainable), each of 6 people on call 1.2 days a week ledger, noisy alerts: 40 pages a week -> 2.9 per 12-hour shift (too many: fix the alerts before handover), each of 6 people on call 1.2 days a week
Read it like this: one missing blocker, the untested database failover, stops the launch on its own; the missing shadow week is a dated follow-up. Six pages a week is under half a page per shift; forty is about three per shift, which is above the level a rotation can sustain, so those alerts are fixed before anyone hands over a pager.
{
"service": "ledger",
"owner": "team-payments",
"receiving_team": "sre-core",
"launch_date": "2026-12-08",
"checks": [
{"area": "SLOs", "item": "availability and latency SLOs agreed", "blocker": true, "evidence": "https://docs.example.com/ledger/slo"},
{"area": "Observability", "item": "burn-rate alerts with runbook links", "blocker": true, "evidence": "https://grafana.example.com/d/ledger"},
{"area": "Capacity", "item": "load test at 2x peak", "blocker": true, "evidence": "https://docs.example.com/ledger/load-test-2026-11-20"},
{"area": "Resilience", "item": "database failover game day", "blocker": true, "evidence": null},
{"area": "Operations", "item": "on-call shadow week", "blocker": false, "evidence": null}
]
}
The format is illustrative and parses as JSON; many teams keep the same list in their catalog or as an issue template. What matters is that each item has an owner, a blocker flag, and a link to evidence anyone can open.
This is a composite of a failure pattern that keeps repeating; the numbers are illustrative. A new payments feature launched on the date marketing had announced, with its readiness work "to follow".
Launch dates are now set after the readiness checklist is estimated, the platform blocks production deploys without an SLO, an owner, and an on-call rotation in the catalog, and customer-facing launches go out by canary with an abort criterion. The next launch moved by a week for a blocker found in review, and had no incident.
Design the production readiness process for an organization launching about 15 new services a quarter, with one central SRE team and many product teams.
Which services are customer-facing or handle personal data? Who carries the pager for each: the building team or SRE? Which checklist items can templates make true by default? How will you know the process reduces incidents? Who may move a launch date?
Say 15 launches a quarter, an SRE team of 8, product teams of 5 to 8, and a target of no more than two pages per 12-hour shift.
A tiered checklist (internal, customer-facing, regulated), started three weeks before launch, with evidence links; golden paths that generate dashboards, SLO alerts, runbook stubs, and canary pipelines; a short review meeting with the receiving team; canary launches with abort criteria; a handover bar with a shadow week and a page budget; re-reviews yearly and after major changes; and a dashboard of 30-day post-launch incidents by review tier.
Full reviews for everything are safe and slow and get skipped; tiers keep them for the risky services. Central SRE ownership gives consistency and creates a bottleneck; building teams owning their pager with SRE support scales better. Hard deploy gates prevent unready launches and need a fast exception path for emergencies.